Use this sand calculator to estimate cubic feet, cubic yards, tons, and approximate 50-lb bag quantities for paver bedding, patios, playgrounds, sandboxes, pool
About this calculator
Use this sand calculator to estimate cubic feet, cubic yards, tons, and approximate 50-lb bag quantities for paver bedding, patios, playgrounds, sandboxes, pool bases, landscape leveling, arenas, and similar projects. Enter the project dimensions and sand depth, then select the closest material type. Sand is sold by volume, weight, or bag, and delivered weight varies with gradation and moisture, so the calculator combines geometric volume with an estimated density rather than assuming every sand product weighs the same.
Multiply length by width by depth to calculate sand volume. The calculator converts depth from inches to feet, reports cubic feet, divides by 27 for cubic yards, and applies the selected density factor to estimate tons. This supports common searches such as a sand calculator in yards, cubic-feet sand calculator, and yards-to-tons sand calculator. For circular areas such as some pools or arenas, calculate the circular area first and multiply it by the required sand depth.
Use cubic yards or tons according to the supplier's sales unit and confirm the supplier's actual material density when delivery weight matters. For paver installations, bedding sand is a distinct layer from compacted aggregate base and from joint or polymeric sand. The general volume result can estimate bedding material, but joint-sand coverage depends on paver dimensions, joint width, joint depth, and the specific product, so manufacturer coverage data should be used for that application. Moisture, compaction, grade variation, and screeding loss can also change final usage.
Worked examples
Paver bedding sand calculator for a patio
A patio is 20 ft long, 10 ft wide, with a 1-in bedding-sand layer.
- Area = 20 × 10 = 200 sq ft
- Convert depth: 1 in ÷ 12 = 0.0833 ft
- Volume = 200 × 0.0833 = about 16.7 cu ft
- Convert to yards: 16.7 ÷ 27 = about 0.62 cu yd
Result: The theoretical bedding-sand volume is about 0.62 cubic yard before an allowance for screeding loss or surface variation.
Playground or sandbox sand calculator
A sandbox is 8 ft by 8 ft and will be filled 8 in deep.
- Area = 8 × 8 = 64 sq ft
- Convert depth: 8 in ÷ 12 = 0.667 ft
- Volume = 64 × 0.667 = about 42.7 cu ft
- 42.7 ÷ 27 = about 1.58 cu yd
Result: The sandbox needs about 1.6 cubic yards of sand by volume before settlement, spillage, or project-specific allowance.
Sand calculator for a pool base
A rectangular 18 ft by 10 ft prepared area needs a 2-in sand layer below the planned installation.
- Area = 18 × 10 = 180 sq ft
- Convert depth: 2 in ÷ 12 = 0.1667 ft
- Volume = 180 × 0.1667 = about 30 cu ft
- 30 ÷ 27 = about 1.11 cu yd
Result: The geometric sand requirement is about 1.11 cubic yards; verify the required base material and depth with the pool or installation specification.